September 11 - A2SEA's Sea Challenger has completed the installation of the 67 Siemens 6 MW turbines at the Dudgeon offshore wind farm.
The final turbine was installed last week on behalf of Statoil, Masdar and Statkraft, owners of the 402 MW facility which is located 32 km off the coast of the UK.
After winning the contract to install the 67 turbines in October 2014, A2SEA completed the installation of the first turbine in January 2017, as HLPFI reported here.
The wind farm is expected to be completed and fully commissioned by the end of 2017.