June 10 - ALE is half way through a project to weigh, transport and install topsides as part of the Malikai deepwater project offshore Malaysia.
ALE is responsible for weighing, skidding and jacking the topsides, as well as mating them to the hull. The company has already weighed and transported four unit hull blocks, living quarters and mega beams for the topsides.
ALE has also been contracted to remove all equipment using its 900-tonne capacity strandjacks, skidding equipment and SPMTs. Once this has been completed, ALE will handle the load-out of the tension leg platform (TLP).