Heavy transport engineering specialist Mammoet played a key role in the construction and load out of components for Equinor’s Hywind Tampen, the largest floating wind farm to date.
The floating wind energy market is still developing and although various component designs, installation techniques and deployment methods are being considered and prototyped, none have been commercialised at full scale. Floating foundations were required for the Hywind Tampen project as the water depth and seabed geology in the Tampen area made it impossible to install conventional fixed-bottom turbines.
Mammoet said that a critical challenge involved assembling the entire 8.6 MW turbines – including tower sections, nacelles and blades - onto 107m spar buoys that lie mainly underwater. This needed to be performed in the controlled environment of a port – where the whole system could be kept as static as possible - before the completed turbines were towed out to their installation site.
With such huge floating foundations, this port required an exceptionally large draught – ruling out jack-up vessels, which would be too short to assemble the turbine sections. Also, though conditions at Gulen Industrial Harbor were calm, using crane vessels would increase the complexity of assembly engineering, which would then require transfer between two floating objects. This could, in turn, delay the integration phase and lengthen the offshore installation campaign, increasing project costs.
A spacer barge between the quay and spar foundation was needed to ensure adequate clearance between the base of the foundation and the seabed. Turbine components would therefore need to be lifted over the quay edge, over the spacer barge, then onto the foundations themselves: a distance of around 143 m.
Following its experience during the deployment of the world’s first floating wind farm, Hywind Scotland (also operated by Equinor), Mammoet was engaged to undertake turbine assembly and associated port handling work.
Mammoet strategy
“We recognised that we would need a crane with a huge outreach to make the required lifts. The majority of land-based cranes in any fleet would not be able to achieve a 143 m distance at these weights, but we knew that if it could be done the project would benefit significantly. This would create a smooth production line from marshalling yard to turbine assembly to commissioning - all at the same location - optimizing the use of offshore assets,” explained Martin Tieman, project manager for Mammoet.
“This led us to look at the use of our PTC 200-DS crane, which is proving to be in high demand for big offshore wind projects such as the Greater Changhua development in Taiwan and Seagreen offshore wind farm in Scotland.”
Weather conditions also posed a challenge. Although large ring cranes are built to withstand strong gusts, components such as these - with a large surface area designed specifically to catch the wind - are another matter, said Mammoet. To counteract this, the PTC 200-DS was modified to ensure precise control of components even when winds were strong – meaning that there would be fewer potential stoppages due to the weather and the turbines could be completed sooner.
These modifications allowed the crane to work with third-party blade yoke and tugger winch systems, which orient the load under hook without the need for taglines operated by hand. This prevents damage to relatively delicate turbine blades, and increases levels of safety on site.
Alongside the PTC 200-DS, 24 axle lines of SPMTs and a range of smaller cranes were used to handle the movement of components in port; as well as an LR1750 crane to assist the PTC during lifts that required rotation of components. This further helped to keep idle time as low as possible for all assets, minimising handling manoeuvres overall.