September 3 - At Essent's new power plant in Moerdijk, The Netherlands, Wagenborg Nedlift has been active with the installation of new boiler modules for the new boiler unit.
With weights up to 243 tonnes per unit, Wagenborg Nedlift provided a 750 tonnes and a 350 tonnes crawler to do the job.
Together with the Spanish construction company of the power plant, these lifting works were carried out completely according to schedule.
In the meantime, Wagenborg Nedlift handled shipment of a heavy transformer from Korea to Moerdijk and says that it was a challenge to get this giant of 278 tonnes onto the foundation. Wagenborg Nedlift's hydraulic lifting gantry was perfect fit for the job and within hours, the transformer was put in place.