Transportation company KCTC sourced Cometto self-propelled modular trailers (SPMT) to load out FPSO components with a combined weight of 63,781 tonnes in South Korea. 

Faymonville

Source: Faymonville

Samkang S&C outsourced the load-out project to KCTC, which mobilsed Cometto’s MSPE EVO2 vehicles from Global, Daemyung and Anjeon. Six modules were transported into position, with 288 to 360 axle lines utilised per move.  

Cometto SPMTs called for FPSO build

Source: Faymonville

The FPSO is being built for the Barossa project – a gas and condensate field in the Bonaparte Basin of the Timor Sea, offshore Australia – in which Singapore’s BW Offshore participates as a developer. The FPSO itself, when complete, will have a main deck length of 340 m, a width of 64 m, and a height of 31.5 m.